Public Notice: SAWS CIP Summary of Wurzbach Pump Station Replacement

SAWS factsheet of Wurzbach Pump Station Replacement with map of parcel area of location

The Wurzbach Pump Station, located at Wurzbach Rd. and Evers Rd., will undergo a major upgrade to replace its aging 7.5-million-gallon water storage tank. The current tank no longer meets state and federal safety standards due to internal corrosion.

 

What’s Happening:

  • The old tank will be safely removed.
  • A brand-new 7.5-million-gallon tank will be constructed.
  • Improvements will include new piping, valves, overflow structure, grading, and electrical updates.

 

Timeline:

  • Project will go out for bids: August 2025
  • Construction is expected to begin: September 2025

 

This critical infrastructure project will help ensure long-term water reliability and safety for the community.

For more information:

210-233-3750
Cecilia Picazo
SAWS Sr. Government Relations Coordinator