Timeline

Timeline for Municipal Facilities Bond Project 2013

 

February 2013  Programming 
March 2013  Release Request for Qualifications - Construction Manager at Risk 
April 2013  Preliminary Design 
May 2013  Selection of Construction Manager at Risk 
December 2013  Final Design 
December 2013  Bidding 
Feb 2014 - Dec 2014  Construction 
Feb 2014 - Jan 2015 Fire Station 
Jan 2015 - Jun 2015  Police Station
July 2015 - Jan 2015  City Services
Feb 2016  Project Completion